HIAD Event Initiating System: Hydrogen System Initiating Event


An empty liquid Hydrogen tanker was returning to the base terminal from a delivery at a space centre. At the departure, the internal vessel pressure was 8 psig. At the first safety check, the…

A liquid hydrogen tanker was loaded at the home base and dispatched to a customer (approximately 790 km). The internal vessel pressure after filling was 8 psig (1. 4 bara). During transit, the…

A liquid hydrogen tanker was travelling from the home terminal to delivery to a customer. After approximately 7 hours and 400 miles, the drivers noticed hydrogen venting from the vent stack. They…

When travelling to a customer, a liquid hydrogen tanker experienced a slight tank pressure increase due to an improper cooling down. The driver was carefully monitoring the pressure and when he…

An empty tanker was returning to the home terminal after delivery to a customer. However, the drivers had failed to properly stabilize the residue pressure in the tank before departing from the…
A liquid hydrogen tanker was travelling back to the base after having made an earlier delivery. At the end of the delivery, the pressure in the tanker had been reduced to 75 psig using the vent stack…
A liquid hydrogen tanker had just departed from the home terminal, when the driver notice vapours coming from the curb side of the trailer control cabinet. The driver stopped the vehicle at the…
A full liquid hydrogen tanker was approaching a stop at a vehicle weight station, when the driver noticed vapours coming from the tank vent. The driver parked the vehicle, inspected the tanker and…

A liquid hydrogen tanker was returning almost empty to the base terminal. The drivers noted a pressure rise in the tanker stopped at a remote area of a rest area and performed a controlled venting…

The second stage of the Saturn V (S-II-T) was under full-duration static test, when one fire near LH2 valves of the LH2 tank and another in the engine area caused the automatic termination of the…

A liquid hydrogen tanker had been slightly overloaded. This forced the drivers to performed a manually venting releasing 5000 cu. ft. of hydrogen. [Zalosh and Short, 1978]

During a leak check of a flash point material testing chamber, the chamber was inadvertently over-pressurised with GH2. The glass port in the door burst, causing damage to the chamber and to the…

A hydrogen pipe burst at a semiconductor plant injuring 1 person

A fire broke out at a pipe of the hydrogen production unit, belonging to the steam methane reformer part of the fluidised catalytic cracking (FCC) plant. The fire occurred when personnel of a…

A manufacturer of fuel cells and hydrogen vehicles issued a recall for 35 of its vehicles, due to a manufacturing defect in the Thermal Pressure Relief Device (TRPD). The defect may cause the…

A cryogenic hydrogen laboratory had a power outage. The cryogenic hydrogen storage was no longer being cooled, therefore temperatures and pressures within the storage system started rising. There…

While a H2 sample was being prepared for an analysis, one of two cryogenic sample bottle disks ruptured and the gas ignited. [Ordin, NASA (1974)]

A CGH2 tube trailer was transferring hydrogen to a customer cylinder skid. The pressure relief on the customer system opened, the escaping hydrogen ignited and burned for approximately 10-15…

A liquid hydrogen tanker was returning empty to its home terminal. When the drivers noted that the inner vessel was building pressure. The drivers advised their supervisor and were advised to find a…
A liquid hydrogen tanker was returning to the base after having deliver data customer site. The tank was empty. Nevertheless, on the road the drivers noticed a continuing elevated pressure. To avoid…