An explosion, followed by a fire, happened in an oven belonging to the hydro-treatment unit. Following a shutdown, the tube, containing only gaseous products and hydrogen, had been affected by…
The event occurred while starting a new production cycle. The production supervisor issued specific instruction on a new production cycle to a technician. The technician did not follow them in the…
Hydrogen leak due to a fault with non-process related battery equipment. After reporting the hydrogen leak, fire crews have been called to a gas terminal. The leak was due to a fault with non-process…
The event occurred during the decommissioning of a nuclear power plant. It involved a tank containing 100 kg of residual sodium from the decommissioned experimental nuclear reactor which was using…
Heavy rains (more than 600 mm in 1 day) had flood a factory manufacturing calcium core electrical conductors. The power supply was cut off. The water came into contact with the calcium stored in 150…
Following a loss of power the failure of a backup battery causes an alarm in a hydrogen storage facility. Consequently, a valve on the purge circuit and 30 m3 of hydrogen is released to the…
The event occurred at the factory producing multilayer circuit boards by a multistep dip operation. An employee inadvertently mixed 55 gal of 50 percent hydrogen peroxide into 110 gal of 30 percent…
The incident occurred in an electrostatic filtration unit. When flushing with air during the start-up phase of a sulphonation plant, an explosion occurred in the upper part of the electrostatic…
The explosion took place in the hydrogen gasometer. The bell in the gasometer was lifted 15-20 m straight up and cracked. The cover fell down on the pipe bridge besides the gasometer. The cylindrical…
The bolts on a not further specified industrial facility failed after approximately 4000 hours in service (approximately 18 months in service). Their failure bolts causedH2S leaks. The bolts…

A Bourdon tube ruptured in pressure gauge after 528 hours of operation in LH2. The alarm sounded, the system was isolated and then vented. [Ordin, NASA (1974)]

The soldiers of the Royal Prussian Air Ship Division stored large amounts of hydrogen gas. They kept some 1000 cylinders in a shed. On 25 May 1894 about 400 of them burst without apparent reason.…
A fire and a series of explosions occurred on a petrochemical plant, causing damage to process vessels, containment walls and process utility piping. It is believed that lightning struck a two story…
A hydrogen compressor had a major malfunction resulting in serious cavitations, vibrations and dead heading of the 1st stage. The incident resulted in 5 of the 8 lower head bolts on the first stage…
On the way home, a trailer/truck overturned due to excessive speed, causing the hydrogen bundles to fall. It was transporting two bundles with 30 cartridges each. One of the bundle valves broke,…
A gaseous tube trailer gone off road in a countryside area and landed on one side. All cylinders were loaded to a pressure of 200 bars. The impact with the ground has caused the rupture of a high…
An employee was preparing a batch of glycol stearate emulsifier in a vessel. Upon completion of product, the quality control lab reported that the pH was too high and the product needed to be…
The incident occurred in a pharmaceutical plant. A disc ruptured on the vent of a reactor and the reaction mixture was projected onto a frontage of the synthesis workshop. It caused a spill of 700 l…
The passenger car rolled down the road without driver and hit the hydrogen bus.