Chemical reaction producing hydrogen, followed by an explosion.
The incident occurred in a pharmaceutical plant. A disc ruptured on the vent of a reactor and the reaction mixture was projected onto a frontage of the synthesis workshop. It caused a spill of 700 l of a mixture of mono-chlor-benzene (which is flammable liquid) and sodium borohydride (which is toxic). The plant operator manually activated the emergency response plan, evacuating the personnel. The internal emergency services set up a foam blanket on the spill, then carry out a water washing. The discharge valves were closed and the product was recovered in the fire retention basins. The site's response teams marked out the impacted area and took VOC measurements. Two hours later, the plant operator lifted the emergency response plan and set up a restriction zone around the building. Nine employees were slightly affected by odours The immediate cause was the formation of amount of hydrogen which could not be vented.
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Causes
Cause Comments
The INITIATING cause was the formation of amount of hydrogen which could not be vented. According to the ARIA source, the root causes of this event were identified as:(1) a lack of training of the operator carrying out the pouring,(2) an inaccuracy on the manufacturing sheet as to the flow rate of pouring and (3) safety barriers rendered ineffective by the foaming phenomenon.