Erroneous emptying of a LH2 tank
After a test of a LH2 vessel, during the warm up phase, the plan was to dispose of the hydrogen through the vent system. However, a leak to atmosphere occurred. This was due to a blind flange having been removed and an incorrect valve was opened allowing an open line from the vent system. [Ordin, NASA (1974)]
Record Quality Indicator
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Causes

The erroneous release of the LH2 was due to an operation which did not take into account temporary modifications of the piping system.