Fire from a hydrogen pipeline
A leak occurred at an underground steel pipeline (6 inch) transporting pressurised hydrogen (75 bar). The leakage lasted for at least several hours, but it cannot be excluded that the leakage started weeks or even months prior to the discovery of the leak. The leakage occurred at a location at which the pipeline entered a building and contained a so called “CP coupling” (a device to interrupt the cathodic protection). This is a specific “weak spot” in a pipeline in which tensions could mount, and resulted in the partial failure of “CP coupling”. The escaping hydrogen gas was ignited by welding activities which at that time were taking place in the vicinity of the leak as part of a construction project to add another pipeline in the corridor. The ignition resulted in a small fire on top of the soil. In the surroundings there were several additional pipelines transporting other gases. Because of this, police and the fire brigade took severe precautionary measures, by confining at home the inhabitant of a near village, and stopping the waterborne and road traffic for several hours. At least 8. 4 kilograms of hydrogen have escaped since the leak was noticed, for approximately 7 hours. It is very possible that the leakage had started much earlier. This suggested that the hydrogen released was probably in excess of 50 kg.
Event Date
October 12, 2007
Record Quality Indicator
Region / Country
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Cause Comments
INITIATING CAUSES The leakage was caused by a mix of several tension factors acting on the pipeline: (i) The main stressing factor was the gradual settlement of the pipeline and the earth surrounding it. The settlement took place over a time span of several years and resulted in the bending of the pipeline at a spot where the pipeline got stuck on a fixed structure, e. g. a feed through in which the pipeline enters a building. The bending forces caused tensions on the CP coupling nearby in the pipeline, which eventually started to leak. (ii) Other possible stressing factors were un-allowed heavy traffic and (iii) the placement of heavy equipment on the soil covering the pipeline. CONTRIBUTING & ROOT CAUSE The investigation identified a lack of coordination between at least four supervising bodies responsible for safety inspections. This resulted in a situation in which each body was not assuming responsibility for overall safety, assuming that the other would do the inspections they were not doing.