Fire at a generator of a power plant
SYNOPTICs The loss of the hydrogen side sealing oil pump and other problems in the sealing oil system resulted in the coolant hydrogen leaking from the generator. The hydrogen leaked for several minutes before it ignited and exploded. A fire followed the large explosion, which burned for five to eight minutes. DETAILES SERIES OF EVENTS The plant was operating at 92% power when a ground fault on a land steam exhauster caused the supply breaker to a motor control centre (MCC) to trip. This supply breaker could not be reclosed. The loss of the MCC resulted in a loss of the hydrogen side seal oil pump for the main generator that is powered from that MCC. Nevertheless, the plant continued operation as the licensee procedures and technical manual of the turbine-generator manufacturer allowed full-load operation with the hydrogen side seal oil pump shut down. When operators initiated implementation of a procedure to restore the seal oil system, a small hydrogen explosion occurred and a reactor power reduction was initiated. Shortly thereafter, with the plant at 85% power, a large explosion and fire occurred and the turbine was immediately tripped. Some of the equipment damaged during the fire and explosion caused several grounds in the i nth electrical power system, resulting in voltage degradation which hindered the fighting of the emergency.
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Cause Comments
INITIATING CAUSE The loss of the pump serving the hydrogen side seal oil was at the basis of the incidents. ROOT CAUSE The fact that the operation allowed even without the seal oil pump was probably a contributing or root cause, because is the responsible of hydrogen leak and accumulation before ignition. The fighting of the emergency resulted in additional deficiencies, probably due to loss of voltage capacity because of the fire. This suggests design or management root causes.