Malfunctioning in a hydrogen refuelling station (404)

This data is from the European Hydrogen Incidents and Accidents database HIAD 2.1, European Commission, Joint Research Centre.

Malfunctioning in a hydrogen refuelling station

At a refuelling station for buses, the first dispenser had been taken out of operation, because leaking (see HIAD event 403). Another dispenser was being used. Fuelling was taking too long and was very slow. The producer was called and it was found that the solenoid valves were not opening correctly due to a lack of compressed air.
Event Date
July 23, 2013
Record Quality Indicator
Event Initiating System
Classification of the Physical Effects
Nature of the Consequences
Cause Comments
It was found that a snap connector on an air line in the fuel cell workshop had come apart overnight. The air supply was restored and fuelling took place normally so that no buses were delayed for service. Before the workshop was locked up there was no indication that the near miss would occur. Investigation found that the connector was fitted with the correct crimp.
Facility Information
Application Type
Application
Hydrogen dispenser
Specific Application Supply Chain Stage
Components Involved
H2 dispenser
Storage/Process Medium
Location Type
Operational Condition
Pre-event Summary
The refuelling station was working on only one dispenser, because the other one had been shut down for repairing a leakage.
Consequences
Number of Injured Persons
0
Number of Fatalities
0
Post-event Summary

The air supply was restored and fuelling took place normally so that no buses were delayed for service.

Event Nature
Release Type
Ignition Source
Detonation
No
Deflagration
No
High Pressure Explosion
No
High Voltage Explosion
No
References
References

Report were available & confidential, and now is lost